2020 on. Kier’s DCP – Damage to Crown Property / Damage to Council Property

Activity Shift
1 Initial Response £1,220.62
2 General Clearance £1,220.62
3 Major Clearance £3,505.84
4 Spillages £3,505.84
5 Earthworks Remedials £2,495.00
6 Replacement of Signs & Posts £2,495.00
7 Replacement of Lit Signs & Posts £2,879.73
8 Replacement of Lighting Columns etc £3,848.96
9 Boundry Fencing Repairs £2,009.88
10 VRS Repairs – steel inc terminals £2,985.72
11 Bridge Parapet Repairs inc terminals £2,337.23
12 Traffic Management (single closure) £3,119.05
13 Traffic Management (double closure) £4,508.03

Initial Response breakdown:

Rate per per per
shift hours hour person
Operatives 2 £472.61 £945.22 9 £105.02 £52.51
Transit Tipper 1 £275.40 £275.40 9 £30.60
‘Shift Cost (Fixed Costs) £1,220.62 9 £135.62