Rates from an Area 9 2018 incident billed in 2019:
Cost Breakdown Document | |
Incident Ref: | |
Incident Date/Time: | |
Insurer: | |
Area & Incident Location: | |
The following incident had occurred as referred to in the above referenced log and date: | |
Initial Incident | |
Description | Base Rate |
AIW’S attending Incident | |
Asset Inspection Watchman 1 | £65.75 |
Asset Inspection Vehicle | £36.91 |
Control Room Operators During Incident | |
NCC Operator | £35.35 |
Planning | |
Description | Base Rate |
AIW Planning of repair | |
Asset Inspection Watchman 1 | £65.75 |
Staff involved with incident identification | |
DCP Manager | £55.75 |
DCP Technical Assistant | £22.05 |
Snr Tech Assistant | £37.12 |
Staff involved in the planning of repair | |
TM programmer | £65.75 |
Assistant to Area Manager | £55.75 |
Network Occupancy Manager | £55.75 |
Supervisor | £55.75 |
Asset Engineer | £43.93 |
Depot Clerk 1 | £22.05 |
Defect Programme Manager | £22.05 |
Storeman | £37.70 |
Repair 1 | |
Description | Base Rate |
Staff involved with pricing completion | |
DCP Manager | £55.75 |
DCP Technical Assistant | £22.05 |
Snr Tech Assistant | £37.12 |
QS Claims Consultant | £93.06 |
Electrical/Structures | |
Supervisor | £54.99 |
TM Gang | |
TM supervisor | £54.99 |
18t TM Truck Sidewell with cushion EUROCARGO | £71.11 |
Operatives | £25.89 |
Additional TM Gang (IPV) | |
TM vehicle | £56.46 |
Operatives | £25.89 |
Traffic Management Equipment | |
TM13 Multiple offside lane closure on a 3 lane Motorway with Hardshoulder | £259.02 |
TM16 Lane 3 of 3 lane Motorway with Hardshoulder | £231.15 |
Barrier Gang | |
Supervisor | £54.99 |
18T Barrier Rig | £56.46 |
No of Operatives | £25.89 |
Materials | |
C01 TCB std Beam | £53.53 |
C03 TCB adj Beam | £52.16 |
A55 C/Res Long Driven Post | £42.93 |
F01 TCB Shear Bolt M8x35mm | £0.19 |
F07 TCB Lap Bolt M16x35mm | £0.48 |